Which permits for an Island Park dirt job take the longest, and when should each one be filed?

The longest published clock is a pond's water right — approximately three months uncontested

— followed by stream-channel work at 60 days' notice. File the county grading permit about a fortnight out, the stormwater NOI about a month out, and 811 two to ten business days before the machine moves. Lead times as published, retrieved August–October 2026.

Every clock on one page

The digging is quick; the paperwork ahead of it sets the date. Every lead time this site has found, longest first:

FilingWhen to fileThe clock, as publishedSource
Storage water right (a pond)About 3 months before groundbreaking"approximately three months" from application, uncontested; a contested one runs longerIDWR, retrieved 23 September 2026
Dam safety plans (pond 10 ft or more high, 50 acre-feet or more)With the engineer's plans"approved or disapproved in no more than 60 days and in no less than 14 days after receipt"Idaho Code §42-1712
Stream Channel Alteration permit"at least 60 days prior to the proposed construction start date""In general, the total process should vary from 20 to 70 days or more."IDWR Joint Application
Stormwater NOI (1 acre or more disturbed)About a month out — "At least 14 days before earthwork starts""authorization takes 14 more after a complete NOI"IPDES E-Permitting System
Low-erosivity waiver (small sites)Before construction begins"The operator must submit a waiver certification to DEQ prior to commencing construction activities." — IPDES CGP, Appendix B.1. Retrieved 16 October 2026IPDES CGP
County excavation and grading permitAbout a fortnight outReview "7–10 working days, stated on the form"; "The Administrator notifies the applicant within 10 business days"County application form
Forest practice notification (clearing)Before any clearing begins"No forest practice may begin until the applicable notification is formally accepted by the Department" — IDAPA 20.02.01, sec. 020.05.b. Retrieved 21 October 2026Idaho Department of Lands
Rock crusher registration"fifteen (15) days before commencing operation"The Department "acknowledges registration in writing within fifteen days"IDAPA 58.01.01
811 locate notice"at least two business days and at most ten before excavation starts"Marks valid 4 weeks; notice reinitiated if digging has not started within 3 weeksIdaho Code § 55-2205
US-20 approach permit (after it issues)"If work does not begin immediately, the permittee must notify the Department before commencing"Work complete within 30 days of starting; "If the permitted work is not complete within a year of issuance, the permit is void"IDAPA 39.03.42
Closing a buried fuel tank"At least 30 days before permanently closing an UST""the federal rule and Idaho's notification list agree"Federal UST rule; Idaho notification list
Demolition paperwork"weeks before the excavator swings""large demolition projects require an asbestos-free certification or proof of proper abatement, plus prior approval from the landfill supervisor, before the first truck delivers anything"Landfill requirements

Why the short season makes filing dates the whole schedule

"Seven to ten working days is a fortnight in practice. In a season this short that is not a rounding error, and it is the single best reason to file early rather than at the point the machine is booked." That logic compounds up the table: the county review is the fastest of the real approvals, and everything above it takes longer.

If you are reading this late

The 811 notice is the only short clock — two business days at the floor. Nothing else compresses: the water right takes the months it takes, and the stream-channel application needs its 60 days whether the machine is booked or not. The honest late-case move is to sequence the project around the longest clock the job actually needs, and start this week on the filings that cost nothing to begin.

Not covered on this site (named gaps)

Questions people ask

How far ahead do I call 811?

Notice "at least two business days and at most ten before excavation starts," with the dig path pre-marked in white; if digging has not started within three weeks of the notice, it must be reinitiated.

Which permit has the longest lead time?

A pond's storage water right — approximately three months uncontested — unless the pond crosses the dam threshold, which puts an engineer and a 14-to-60-day plan review at the front of the schedule.

How far ahead should the stormwater NOI go in?

About a month: 14 days before breaking ground is the floor, and authorization takes 14 more days after a complete NOI.

How long does the county grading permit take?

Review of 7–10 working days, stated on the form, with the Class I decision due within 10 business days — a fortnight in practice.

Do locate marks expire?

Yes — the markings are valid for no more than four consecutive weeks from the date of notification, and notice must be reinitiated if excavation has not commenced within three weeks.