From NOI to NOT: the machinery the stormwater permit puts on your job
Where the one-acre line leaves off
The one-acre line answers a yes-or-no question: does your project need a state stormwater permit at all? This page picks up the moment the answer is yes. What follows is not a summary of good intentions — it is the machinery of Permit No. IDR100000, the IPDES Construction General Permit, which DEQ issued January 10, 2022, made effective February 10, 2022, and runs through its expiration date of February 9, 2027. The permit’s own cover page sets the tone:
“A copy of this general permit must be kept at all construction activities covered by this permit”
— IPDES Construction General Permit, Permit No. IDR100000. Retrieved 16 October 2026
A copy of the permit, on the dirt, at the job. Here is the whole machine on one row each, then section by section:
| Duty | The rule | The clock |
|---|---|---|
| SWPPP | Written, complete, and kept current at the site or an easily accessible location | Done before the NOI; updated within seven days of changes |
| NOI | Filed through the IPDES E-Permitting System | At least 14 days before earthwork starts |
| Authorization | Coverage attaches only after DEQ receives a complete NOI and fees are paid | At least 14 days after the complete NOI |
| Fee | $200 first year for up to 10 disturbed acres; annual fees follow | Assessed October 1, due December 30 |
| Inspections | Weekly, or biweekly plus every 0.25-inch storm discharge day | Report written within 24 hours of each inspection |
| Stabilization | Start the moment an area sits idle 14+ days | Finished within 14 days — 7 days above five acres open at once |
| Final stabilization | 70 percent native vegetative cover, or rock/geotextile equivalents | Before the NOT can honestly be filed |
| Termination | NOT through the E-Permitting System once a Section 8.2 condition is met | Within 30 days; coverage dies at midnight on receipt |
The SWPPP comes before anything else
The Stormwater Pollution Prevention Plan is not a follow-up document. DEQ’s permitting page states the sequence flatly — a SWPPP “must be completed before submitting a Notice of Intent” — and the permit itself adds detail that surprises first-time applicants: the plan has to carry the construction schedule and “total acreage (to the nearest quarter acre) to be disturbed” — not a rounded guess, a quarter-acre figure. What DEQ expects inside the document:
- Identification of potential pollution sources — what is on the site that can move when water does.
- Description of control measures (BMPs) — the silt fence, inlet protection, and stabilization plan.
- A site map showing drainage and discharge points — where the water enters and leaves.
- Inspection and maintenance procedures — who walks the site, how often, and what gets written down.
- Corrective action procedures — what happens when a control fails.
Build the SWPPP while the machine is still parked. It is the document the whole rest of this page hangs off.
The NOI clock
Coverage starts with a Notice of Intent through DEQ’s E-Permitting System, and the permit’s Table 1 sets two clocks that do not overlap:
“At least 14 calendar days… prior to commencing… construction activities.”
— IPDES CGP, Table 1, NOI submittal deadline for a new site. Retrieved 16 October 2026
“At least 14 calendar days… after DEQ notifies you that it… has received a complete NOI.”
— IPDES CGP, Table 1, permit authorization date. Retrieved 16 October 2026
Read those together and the planning implication lands: file the NOI about a month before the first blade cuts ground, because authorization does not attach to the moment you submit — it attaches to DEQ’s receipt of a complete NOI plus fourteen more days. DEQ’s page adds that “The 14-day external agency review begins when the NOI is deemed complete” — an incomplete NOI stops the clock from ever starting.
One wrinkle matters when a project changes hands mid-job. A new operator of an already-permitted site must file “No later than 30 calendar…days after commencing…construction activities.” While that filing is in flight the permit keeps the work legal: the new operator is considered provisionally covered under the permit’s terms immediately, and fully covered at least 14 calendar days after DEQ receives the NOI.
The fee that unlocks coverage
Filing is not paying, and the distinction is not cosmetic:
“Coverage under a general permit is not authorized until all required fees have been paid”
— Idaho DEQ, IPDES Permits and Fees. Retrieved 16 October 2026
For the Construction General Permit, the first-year fee scales with disturbed acreage, and an annual fee follows:
| Acres disturbed | First-year fee | Annual fee |
|---|---|---|
| More than 0 to 10 acres | $200 | $0 |
| More than 10 to 50 acres | $400 | $75 |
| More than 50 to 100 acres | $750 | $100 |
| More than 100 to 500 acres | $1,000 | $400 |
| More than 500 acres | $1,250 | $400 |
Most Island Park dirt-work jobs live in that first row — but the second year is where people get surprised, because “IPDES fees are established under IDAPA 58.01.14.170… Annual fees are assessed October 1 and are due by December 30.” A project that holds coverage across an October 1 gets a bill, even if nothing moved that month.
Who inspects, and how often
The permit does not require a consultant in a white truck. On who may conduct the inspections:
“The person inspecting your site may be a person on your staff or a third party you hire to conduct such inspections”
— IPDES CGP, sec. 4.1. Retrieved 16 October 2026
Whoever it is must meet a training floor in Section 6.3 — the first route is to “Complete an EPA construction inspection course developed for the EPA CGP and have passed the exam”, with a current construction inspection certification or a supervised team member as alternatives. The frequency is a menu of two:
“At least once every seven calendar days; or…Once every 14 calendar days… and once each day that there is a discharge from your site to a water of the U.S. from a storm event of 0.25 inches or greater of rain”
— IPDES CGP, sec. 4.2. Retrieved 16 October 2026
Weekly is the simple choice; the biweekly choice drags a rain trigger behind it. And the permit does not take your word for the weather: “you must keep a properly maintained rain gauge on your site or obtain the storm event information from a weather station that is representative of your location”. Three small clocks run alongside the big ones:
- The paperwork clock — every inspection becomes a report within 24 hours.
- The track-out clock — sediment dragged onto paved roads gets removed by the end of the same business day.
- The repair clock — routine fixes get done by the end of the next business day; new or replacement controls within seven days.
This is a permit written by people who have watched job sites.
Keeping the SWPPP alive and reachable
The SWPPP is a living document with an address:
“You must keep a current copy of your SWPPP at the site or at an easily accessible location”
— IPDES CGP, sec. 7.3. Retrieved 16 October 2026
Not just the plan — notice of it: the location “must be posted near the main entrance of your construction site”. And the plan changes on a deadline — “You must modify your SWPPP, including the site maps, within seven days” of any of these:
- New operators become active in construction activities on the site.
- Changes are made to the construction plans or storm water controls.
- A control is found inadequate, or site conditions simply stop matching the map.
A SWPPP written in May and never touched again is, by August, usually fiction.
Stabilization: the deadlines that end the exposure
Bare dirt is the liability; stabilization is the cure, and the permit’s Table 2 sets two speeds depending on how much land is open at once. For sites holding disturbance to five acres or less at any one time:
“Initiate the installation of stabilization measures immediately… in any areas of exposed soil where construction activities have permanently ceased or will be temporarily inactive for 14 or more calendar days”
— IPDES CGP, Table 2. Retrieved 16 October 2026
“Complete the installation of stabilization measures as…soon as practicable, but no later than 14 calendar days…after stabilization has been initiated”
— IPDES CGP, Table 2 (five acres or less disturbed at any one time). Retrieved 16 October 2026
Open more than five acres at once and the completion window tightens to “no later than seven calendar days after stabilization has been initiated”. And “immediately” is defined, not vibes — the permit’s own footnote reads “as soon as practicable, but no later than the end of the next business day” after work in that area stops.
What “done” means — and the NOT
Final stabilization is a measured condition, not a feeling:
“Establish uniform, perennial vegetation (i.e., evenly distributed, without large bare areas) that provides 70 percent or more of the cover that is provided by vegetation native to local undisturbed areas”
— IPDES CGP, sec. 2.2.14.C, final stabilization criteria. Retrieved 16 October 2026
Where grass is not the answer, the permit accepts equivalents: “permanent non-vegetative stabilization measures (e.g., riprap, gravel, gabions, and geotextiles) have been implemented to provide effective cover for exposed portions of the site” — which is why so many Idaho road shoulders wear rock instead of lawn. Once done, closing out is itself a deadline:
“You must submit an NOT within 30 calendar days after any one of the conditions in Section 8.2 occurs”
— IPDES CGP, sec. 8.4. Retrieved 16 October 2026
The Section 8.2 conditions, in plain terms:
- Finished — earth-disturbing activities are complete and the final stabilization conditions are met.
- Transferred — another operator has taken over the site and obtained their own coverage.
- Re-permitted — the discharge now sits under a different IPDES permit.
DEQ’s fees page adds the practical warning: permit coverage remains active until DEQ approves the NOT — and with it, the annual fee clock. The ending is exact to the hour: “Your authorization to discharge under this permit terminates at midnight on the day DEQ receives the NOT through the E-Permitting System.” Projects that finish in October and never file the NOT are still covered — and still billed — the following year.
Why this page belongs on an excavation site
Every item above lands on the dirt-work contractor, not the homeowner: the SWPPP’s site map, the inlet and perimeter controls, the track-out sweep, the quarter-acre arithmetic, the seed or rock that closes the file. It stacks on top of the local rules this site already walks through — the drainage rules for a new road, the SPCC plan for fuel storage, and the air-permit side of crushing and dust — and underneath all of them sits the one-acre line that decides whether any of it applies.
Work the permit into the schedule, not after it
- Run the acreage early — the one-acre line and the common-plan rule decide whether this whole page is your problem.
- Draft the SWPPP before mobilizing — it must be complete before the NOI is even submitted.
- File the NOI about a month out — 14 days before breaking ground is the floor, and authorization takes 14 more after a complete NOI.
- Pay the fee and keep the proof — coverage is not authorized until payment clears.
- Pick the inspection rhythm — weekly, or biweekly with a rain gauge and a 0.25-inch trigger — and write every report within 24 hours.
- Stabilize on the clock — next business day to start, 14 days (or 7, above five acres) to finish.
- File the NOT within 30 days of done — coverage ends at midnight the day DEQ receives it, and so does the fee cycle.
- Want it handled end to end? (208) 932-1140 — crews that plan dirt work around permit clocks instead of against them.
Related reading: the one-acre line and the county runoff plan that come first, when fuel storage on the job pulls in an SPCC plan, and the air rules that follow a rock crusher.
Common questions
When must the NOI be filed for an Idaho construction stormwater permit?
At least 14 calendar days before construction activities commence - and authorization does not arrive until at least 14 calendar days after DEQ notifies you it has received a complete NOI. File roughly a month before ground breaking so the two clocks do not collide with your mobilization date.
What comes first, the SWPPP or the NOI?
The SWPPP. DEQ is explicit that it must be completed before submitting a Notice of Intent. The plan needs the pollution sources, the control measures (BMPs), a site map showing drainage and discharge points, and inspection and maintenance procedures, plus the disturbance acreage to the nearest quarter acre.
How much does the Idaho Construction General Permit cost?
First-year fees scale with disturbance: $200 for more than 0 to 10 acres, $400 to 50 acres, $750 to 100 acres, $1,000 to 500 acres, $1,250 above that. Annual fees follow under IDAPA 58.01.14.170 - assessed October 1 and due by December 30 - and coverage is not authorized until the required fees are paid.
Who is allowed to inspect a CGP site in Idaho?
A person on your staff or a third party you hire, provided they meet the Section 6.3 training floor - completing an EPA construction inspection course developed for the EPA CGP and passing its exam, holding a qualifying certification, or working under a trained storm water team member.
How often are stormwater inspections required?
At least once every seven calendar days, or once every 14 calendar days plus once each day the site discharges to a water of the U.S. from a storm of 0.25 inches or greater of rain. A maintained on-site rain gauge (or a representative weather station) decides, and each inspection report is due within 24 hours.
Does the SWPPP have to be physically kept on the site?
A current copy must be kept at the site or at an easily accessible location, and notice of the plan's location must be posted near the main entrance of the construction site. The plan must also be modified, maps included, within seven days of changed operators, plans, or controls.
How quickly must disturbed soil be stabilized?
Initiate stabilization immediately - defined as no later than the end of the next business day after work in an area stops for 14 or more calendar days - and complete it within 14 calendar days (seven calendar days if more than five acres are disturbed at any one time).
What counts as final stabilization under the permit?
Uniform perennial vegetation providing 70 percent or more of the cover provided by vegetation native to local undisturbed areas, or permanent non-vegetative measures - riprap, gravel, gabions, geotextiles - providing effective cover for the exposed portions of the site.
When and how do I get out of the permit?
File a Notice of Termination through the IPDES E-Permitting System within 30 calendar days after a Section 8.2 condition occurs - final stabilization met, the site transferred to a covered operator, or coverage under another permit. Authorization terminates at midnight on the day DEQ receives the NOT.
Does a new operator on an ongoing project need their own coverage?
Yes. A new operator must submit an NOI no later than 30 calendar days after commencing construction activities, and is considered provisionally covered under the permit immediately, becoming fully covered at least 14 calendar days after DEQ receives the NOI.
Does the permit pause in winter?
No, but it flexes. Inspections may be suspended or cut to monthly under continuous frozen conditions if the site is stabilized and disturbances have stopped - with immediate resumption the moment thaw or rain makes discharges likely. The winter mechanics are a story of their own.