What does Idaho stormwater permit coverage cost for a construction site in Island Park?
What does the coverage cost?
Coverage is owed once a project disturbs an acre or more, including smaller sites inside a common plan of development (the one-acre line). The fees scale with acres disturbed under Permit No. IDR100000 — "the IPDES Construction General Permit, which DEQ issued January 10, 2022, made effective February 10, 2022, and runs through its expiration date of February 9, 2027."
The fee schedule, as published:
| Acres disturbed | First-year fee | Annual fee |
|---|---|---|
| More than 0 to 10 acres | $200 | $0 |
| More than 10 to 50 acres | $400 | $75 |
| More than 50 to 100 acres | $750 | $100 |
| More than 100 to 500 acres | $1,000 | $400 |
| More than 500 acres | $1,250 | $400 |
(Idaho DEQ IPDES fee schedule, retrieved 16 October 2026, via /what-the-construction-stormwater-permit-requires, published 2026-10-16.)
Paying gates coverage: "Coverage under a general permit is not authorized until all required fees have been paid" — Idaho DEQ, IPDES Permits and Fees. Retrieved 16 October 2026.
What moves the total?
- Acres disturbed. The table is the whole price ladder — every tier is set by it.
- Sitting across an October 1. Annual fees are "Assessed October 1, due December 30" — Idaho DEQ fee page, retrieved 16 October 2026 — and "A project that holds coverage across an October 1 gets a bill, even if nothing moved that month."
- When you file the NOT. "You must submit an NOT within 30 calendar days after any one of the conditions in Section 8.2 occurs" — IPDES CGP, sec. 8.4. Retrieved 16 October 2026. The clock runs to approval, not filing: "permit coverage remains active until DEQ approves the NOT — and with it, the annual fee clock."
- Whether the waiver fits. Under 5 acres, $125 may replace the $200.
The $125 waiver against the $200 permit
"Projects that disturb less than 5 acres and have a Rainfall Erosivity Factor (R factor) of less than 5 may qualify for a low erosivity waiver (LEW)" — Idaho DEQ, IPDES Permits and Fees. Retrieved 16 October 2026. The price comparison, exactly as quoted: "$125, with no annual fee - against $200 for a first-year Construction General Permit covering up to 10 disturbed acres." Certification goes through the IPDES E-Permitting System before construction activities commence.
Its edge: "if the R factor is five or greater, you do not qualify for the rainfall erosivity waiver, and must obtain coverage under an IPDES permit." R is run on EPA's calculator for the actual address and dates, so the schedule is a cost lever: "You may find that moving your construction activity by a few weeks or expediting site stabilization will allow you to qualify for the waiver" — IPDES CGP, Appendix B.1. Retrieved 16 October 2026.
What the sources don't price
- A written SWPPP or a hired inspector. Inspections may be in-house — "The person inspecting your site may be a person on your staff or a third party you hire to conduct such inspections" (IPDES CGP, sec. 4.1, retrieved 16 October 2026) — but a hired SWPPP writer's or inspector's charge is a quote item, not a published price.
- The fee schedule after February 9, 2027. The permit expires that day; the schedule that follows is not in our sources — check DEQ's current fees page then.
- Fremont County's own runoff and erosion control plan fee. Not in our sources; ask the county.
How do you get to a real number?
- Place the project in the fee table by acres disturbed — common-plan acreage included.
- Under 5 acres, run the R factor on EPA's calculator for your actual dates before paying $200.
- When the job is done, file the NOT within 30 calendar days and confirm DEQ approved it — that stops the fee clock.
- For the dirt work behind the permit, call or text (208) 932-1140.
Questions people ask
- How much does stormwater coverage cost for a small job site? $200 first year for up to 10 disturbed acres, no annual fee in that tier (as of 16 October 2026).
- Is there a cheaper option than the $200 permit? Maybe: the low-erosivity waiver is "$125, with no annual fee," for projects under 5 acres with an R factor under 5.
- When does the annual fee get billed? "Assessed October 1, due December 30" — and a project that holds coverage across an October 1 is billed "even if nothing moved that month."
- How do I stop the annual fee? File the NOT within 30 calendar days of a qualifying condition; coverage stays active — and billable — until DEQ approves it.
- Can I do the required inspections myself? Often yes: "The person inspecting your site may be a person on your staff or a third party you hire" (IPDES CGP, sec. 4.1).
- Do these fees change when the permit expires in 2027? The current permit (IDR100000) runs through February 9, 2027; the schedule after that date is not in our sources.
Where to read next
- What the construction stormwater permit requires — /what-the-construction-stormwater-permit-requires
- The low-erosivity waiver in full — /the-low-erosivity-waiver-skipping-the-stormwater-permit
- Talk to a local operator — (208) 932-1140