The floodplain development permit: what the county requires before the dirt moves
The permit that arrives with the map, not the building
Most county permits attach to structures: a house, a shop, an approach. The floodplain development permit attaches to ground. When any part of a parcel sits inside a mapped flood hazard area, the county’s floodplain rules reach everything done there — and for dirt work they reach it first. The map question itself — what FEMA’s flood mapping does and does not show for Fremont County — is its own subject; this page is about what the county requires once the answer is yes.
The county wraps its mapped hazard areas in a dedicated chapter of the Development Code — the Floodplain Overlay District — that stacks on top of zoning and on top of the ordinary dirt-moving permit. The chapter’s widest reach sits at the dirt level, because of one sentence:
“The exemptions of 3.04.010, 3.04.030, 3.04.050, and 3.04.060 shall not apply within any stream or lakeshore corridor or special flood hazard area established by this Ordinance. All application activity within stream or lakeshore corridors or special flood hazard areas shall be subject to the requirements for a permit”
— Fremont County Development Code, sec. 3.04.080. Retrieved 21 October 2026
Translated: the exemptions landowners rely on everywhere else die at the hazard-area boundary. Which ones:
- Agricultural clearing and grading — exempt on ordinary ground, permitted here, irrigation works included.
- Small accessory buildings — the little-shed exemption does not travel into the hazard area.
- Minor utility installations — a permit question once the ground is mapped.
- Signs — same.
- What keeps its exemption — remodeling that leaves a building’s footprint alone, and short fences; nearly everything else needs paper.
The federal floor the county enforces
The chapter’s first division is titled Administration of Federal Flood Insurance Program Requirements: the county is administering the federal minimum criteria at 44 CFR 60.3, and two of its orders shape every application. The first is sequencing:
“Review proposed development to assure that all necessary permits have been received from those governmental agencies from which approval is required by Federal or State law”
— 44 CFR 60.3(a)(2). Retrieved 21 October 2026
In practice the county does not open its floodplain review until the other agencies’ approvals are already in the file. Ground that floods is often ground that is also wetland under the Army Corps’ rules, and dirt moved in the hazard area can trip the construction stormwater permit on its own track — none of them waits for the county, and the county waits for all of them. The second order is the standard running through everything below:
“Review all permit applications to determine whether proposed building sites will be reasonably safe from flooding”
— 44 CFR 60.3(a)(3). Retrieved 21 October 2026
What the dirt work itself must satisfy
Drainage is a design submitted with the application, not a result discovered in the spring. The chapter’s site-planning standard:
“the site shall be graded and drained to guide floodwaters around and away from existing and/or proposed buildings”
— Fremont County Development Code, sec. 7.12. Retrieved 21 October 2026
Graded and drained to guide floodwaters around and away — the site plan shows where the water goes before the machine moves, not after the spring proves it. Hazardous substances are out entirely:
“The storage and handling of hazardous substances in the FOZD shall be prohibited”
— Fremont County Development Code, sec. 7.11. Retrieved 21 October 2026
For a job site, that is a staging question, and the answers are short:
- Fuel, chemicals, tanks — the code prohibits hazardous substances without defining them; treat fuel, chemicals, and tanks as hazardous substances and stage them outside the boundary.
- Commercial solid waste handling — may not be located in the district at all.
And altered watercourses keep their obligation after the work ends:
“Continuing maintenance to prevent the reduction of flood carrying capacity in altered or relocated watercourses shall be required”
— Fremont County Development Code, sec. 7.16. Retrieved 21 October 2026
Realign a channel as part of the project and the capacity it carried must stay carried — a standing duty, not a final-inspection item. The state’s own stream channel alteration permit runs alongside on a separate track.
The floodway: where fill itself is the question
Inside the mapped hazard area sits a stricter zone, and for an excavator it is the one that matters most:
“The floodway is the channel of a river or other watercourse and any adjacent land area that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than one foot”
— Fremont County Development Code, sec. 7.15. Retrieved 21 October 2026
“Encroachments into the floodway, including fill, new construction, substantial improvements, and other application shall be prohibited, unless an engineer or architect certifies that the encroachment will not result in any increase in the flood level during the base flood discharge”
— Fremont County Development Code, sec. 7.15. Retrieved 21 October 2026
Read the second one as an excavator:
- Prohibited by default — fill, new construction, substantial improvements, any other application inside the floodway.
- One door through — an engineer’s or architect’s certification, on analysis, that the encroachment raises the flood level not at all during the base flood discharge.
- Not a little — not at all: the standard is zero rise, certified; a promise of best efforts is not a certification.
A push of fill into the wrong part of the channel is not a permit question; it is a prohibition with a certification exception.
What the buildings must clear
The elevation standards decide pad height, and pad height is dirt work:
“Construction or substantial improvement of any dwelling shall result in the lowest floor being elevated to or above base flood elevation”
— Fremont County Development Code, sec. 7.13.010. Retrieved 21 October 2026
Where FEMA has put a number on the flood, the lowest floor — basement included — clears it. Enclosed space below that floor is prohibited outright unless it is designed to let floodwater in and out on its own, and the openings spec is exact:
- Two openings minimum — in every enclosed area below the lowest floor.
- A square inch per square foot — total net area, for every square foot of enclosed area subject to flooding.
- Bottoms within a foot of grade — no higher, so water enters and leaves on its own; a crawlspace that cannot flood on purpose is a violation, not a feature.
“A minimum of two openings, having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding, shall be provided”
— Fremont County Development Code, sec. 7.13.030. Retrieved 21 October 2026
Where no flood elevation number exists, the county requires a showing instead:
“applications shall be reviewed to assure that the proposed construction will be reasonably safe from flooding. This determination of reasonableness shall be based on evidence submitted with the application by the Applicant, including historical flood records, photographs of past flood events, and similar documentation. The minimum elevation above grade in such cases shall be two feet”
— Fremont County Development Code, sec. 7.13.050. Retrieved 21 October 2026
Reasonable safety, argued from evidence — flood records, photographs of past high water — with a hard floor underneath it: two feet above grade, minimum. Manufactured homes get their own line:
“Manufactured homes that are placed, replaced, or substantially improved within the FOZD shall be elevated on and securely anchored to a permanent foundation, so that the lowest floor is at or above base flood elevation. Manufactured home (mobile home) parks shall not be permitted in the FOZD.”
— Fremont County Development Code, sec. 7.13.060. Retrieved 21 October 2026
Nonresidential buildings may take the other road — dry flood-proofing instead of elevation:
“Be flood-proofed so that below base flood level, the building is watertight, with walls substantially impermeable to the passage of water”
— Fremont County Development Code, sec. 7.14.010. Retrieved 21 October 2026
Watertight, substantially impermeable walls, engineered against hydrostatic and hydrodynamic loads — and the code requires the county to tell flood-proofing applicants that insurance premiums will be based on rates one foot below the flood-proofed level. The discount never fully arrives.
Shallow-flooding ground: the AO and AH zones
Some mapped hazard is sheet flow, not a river:
“In these areas, base flood depth ranges from one to three feet, a clearly defined channel does not exist, the path of flooding is unpredictable and indeterminate, and velocity flow may be evident”
— Fremont County Development Code, sec. 7.17. Retrieved 21 October 2026
“Have the lowest floor elevated above the highest adjacent grade of the building site to or above the depth number specified on the FIRM or, where no depth number is specified, to at least two feet above the highest adjacent grade”
— Fremont County Development Code, sec. 7.17.010. Retrieved 21 October 2026
On flat ground next to sloped ground, that grade measurement is the number the pad gets built to:
- A depth number on the map — the floor clears the highest adjacent grade by that many feet.
- No number given — at least two feet above the highest adjacent grade, whatever the sheet flow does.
Variances exist — and are priced
The county can vary the chapter’s requirements, but a floodplain variance needs an extra finding on top of the usual ones: no increased flood levels, no threat to public safety, no extraordinary public expense. And where the elevation requirement itself is relaxed, the county is required to deliver a warning with the approval:
“the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation”
— Fremont County Development Code, sec. 7.19. Retrieved 21 October 2026
The permits stack; none of them cancels another
- Slope ground too — the same county review that asks the floodplain question asks the steepness question; one hillside can carry both answers.
- Wetlands and stormwater — separate federal and state tracks, sequenced ahead of the county’s review, not merged into it.
- Stream work — channel alteration is its own state permit; the floodplain standards ride on top of it.
Before the machine crosses the boundary
- Settle the map question first — which ground is in the mapped hazard area, from the source mapping, before design assumptions harden.
- Assume the exemptions are gone — clearing, grading, fill, small sheds: plan every piece as permitted work inside the boundary.
- Sequence the outside permits — federal and state approvals into the file before the county’s floodplain review opens.
- Design where the water goes — grading that guides floodwaters around and away, openings sized per square foot, equipment elevated or protected.
- Keep the laydown yard outside — treat fuel, chemicals, and tanks as hazardous substances: they stage outside the boundary.
- Treat floodway fill as an engineering question — certification of no rise, or no fill.
- Ground in the hazard area to move? (208) 932-1140 — floodplain-aware dirt work, sequenced with the paperwork.
Related reading: what FEMA’s flood maps show for Fremont County, the county excavation and grading permit, and when steep ground changes the county review.
Common questions
Do I need a floodplain development permit just to grade, clear, or place fill on my own land?
If the work sits in a mapped special flood hazard area, yes. The county code strips the usual exemptions there - agricultural clearing and grading, small sheds, minor utility installations, and signs all lose theirs - and all application activity in the hazard area becomes subject to the requirements for a permit. Establish the map status first, then plan on the permit.
Can I place fill inside the floodway?
Only with a certification. The floodway is the channel plus the adjacent land reserved to discharge the base flood without raising the water surface more than one foot, and encroachments into it - including fill, new construction, and substantial improvements - are prohibited unless an engineer or architect certifies the encroachment will not result in any increase in the flood level during the base flood discharge.
What elevation does a new dwelling need in the hazard area?
Where base flood elevation data exist, the lowest floor including the basement must be elevated to or above base flood elevation, and enclosed areas below it need flood openings - a minimum of two, with a total net area of at least one square inch per square foot of enclosed area. Nonresidential buildings may instead be flood-proofed watertight with substantially impermeable walls.
What if FEMA has not computed a flood elevation for my ground?
The county then reviews the application to assure the construction will be reasonably safe from flooding, based on evidence you submit - historical flood records, photographs of past flood events, and similar documentation - with a minimum elevation of two feet above grade. In AO and AH shallow-flooding zones, the floor goes above the highest adjacent grade by the map's depth number, or at least two feet where none is specified.
Does the floodplain district restrict what can be stored on the job site?
Yes, and absolutely: the storage and handling of hazardous substances in the district is prohibited, and commercial or industrial solid waste handling facilities may not be located there at all. Fuel, chemical, and tank staging needs a home outside the mapped hazard area - plan the laydown yard accordingly.
Can the floodplain requirements be varied?
A variance is possible, but it requires an additional finding that approval will not result in increased flood levels, a threat to public safety, or extraordinary public expense - and where elevation requirements are relaxed, the county must notify the applicant that the cost of flood insurance will be commensurate with the increased risk from the reduced lowest floor elevation.