How do you get permission to run a utility line across a Fremont County road to your lot?
Step 1 — Confirm whose road it is
The county's permit covers county roads. If the crossing lands on the state highway — US-20 through this valley — the desk changes to ITD's encroachment permit: "An approved right-of-way encroachment permit is required for all utility encroachments prior to the initiation of any work within the state highway right-of-way, and that includes new installation, relocation, maintenance, modification and removal." — islandparkexcavation.com/getting-a-utility-across-us-20 (published 2026-09-04). That page owns the ITD route.
Step 2 — Ask about boring before the trencher is booked
The county can take trenching off the table: "Fremont County reserves the right to require boring of the roadway, rather than trenching through the existing pavement, when trenching may compromise the integrity of the road surface." The practical order matters: "Ask Public Works whether the pavement will require boring rather than trenching before the trencher is booked, not after." — islandparkexcavation.com/utilities-in-the-county-right-of-way (published 2026-09-08). A bore requirement moves the bid more than the permit does.
Step 3 — Apply for the right-of-way permit from Public Works
The permitting line, as published: "A right-of-way permit issued by the Fremont County Public Works Department is required for any construction activity within any of Fremont County’s public roads or right-of-ways. This pertains to activities such as placement of utilities, service lines, private approaches or irrigation facilities." — Fremont County Development Code, 2011 Edition (Ordinance 2011-04), Appendix B, section 1.09, amended by Ordinance 2020-07. Consolidated through Ordinance 2026-03. Retrieved 7 September 2026 — via islandparkexcavation.com/utilities-in-the-county-right-of-way (published 2026-09-08).
Not in our sources, and not printed here as a number: the permit's fee, its review time, its form number, and a Public Works desk phone. Ask the department when you file.
Step 4 — Place the line where the code puts it
Dry and wet lines get separate assigned places:
- "Where the right-of-way is at least 70 feet wide, dry utilities — electricity, gas, and communications — are granted a 5-foot easement adjacent to and within the right-of-way lines. Power and gas may not share the same 5-foot easement."
- "Wet utilities — water, sanitary sewer, storm sewer, and steam — are granted a 3-foot easement adjacent to the outside edge of the shoulder. Water and sewer may not share the same 3-foot easement."
- On narrower roads: "New above-ground utilities must sit at least 15 feet from the shoulder or 24 feet from the centerline, whichever is greater, and still within the right-of-way. Underground dry utilities should go within 4 feet of the right-of-way line."
(all — islandparkexcavation.com/utilities-in-the-county-right-of-way, published 2026-09-08)
Step 5 — Meet the cover and casing rules
The county's permit form states its own minimum covers:
| What crosses the road | Minimum cover, as published |
|---|---|
| Irrigation lines or utility conduit | "three (3) feet" |
| A metal or concrete culvert | "one (1) foot" |
| Buried cable | "eighteen (18) inches" |
— Fremont County, Permit to Use the Right-of-Way (retrieved 2026-08-13), via islandparkexcavation.com/how-deep-do-utility-trenches-go (published 2026-08-19).
Casing is its own condition: "Casing pipe shall be required for all pressurized liquid pipelines crossing the roads, except for domestic water lines up to 2 inches in diameter. All material shall be new. The proposed project must be installed under any culverts that are crossed." — same source.
Step 6 — Give the 811 notice, and keep it fresh
The permit does not open the trench by itself. "The notice shall be communicated by the excavator to the one-number notification service" — "not less than two (2) business days nor more than ten (10) business days before the scheduled date for commencement of excavation" — Idaho Code § 55-2205(1)(c), retrieved August 2026 — via islandparkexcavation.com/call-811-before-digging (published 2026-08-13). Without it: "A permit shall not be valid for excavation until or unless the notice provisions of this section have been complied with" — and "The issuing public agency shall reinstate the permit at no charge within forty-eight (48) hours of receiving evidence of compliance." — islandparkexcavation.com/how-long-locate-marks-stay-valid (published 2026-09-17).
Then the clock: "If excavation has not commenced within three (3) weeks from the original notice to underground facility owners through the one-number notification service, the excavator shall reinitiate notice in accordance with this section." (same page) Near anything marked: "Determine by hand digging, in the area twenty-four (24) inches or less from the facilities, the precise actual location of underground facilities that have been marked" — Idaho Code § 55-2207(2), retrieved 11 September 2026 — via islandparkexcavation.com/the-24-inch-hand-dig-zone-around-marked-utilities (published 2026-09-15).
Where this goes wrong
- Booking the trencher before the boring question. The county reserves the boring call; ask before equipment is scheduled, not after.
- Digging on a permit with no 811 notice. The permit "shall not be valid for excavation" until notice is given — the fix is free within 48 hours of compliance evidence, but the delay is real.
- Sharing an easement the code splits. Power and gas cannot share the 5-foot dry easement; water and sewer cannot share the 3-foot wet one.
- Crossing over a culvert. The code's line is "installed under any culverts that are crossed" — under, not over.
What the sources don't give
- The right-of-way permit's fee, review time or form number, and no Public Works desk phone — confirm each with the department.
- Whether the county inspects a road crossing before it is backfilled.
- A county cover depth for a private service line on the owner's own lot beyond the road.
Who files what
The 811 notice "shall be communicated by the excavator" — it travels with whoever runs the machine, hired operator or owner. Put who pulls the permit and who gives the notice in the bid, in writing. For a read on utility trenching around Island Park, call (208) 932-1140.
Questions people ask
- Does a utility line in a county road need a permit in Fremont County? Yes — the Public Works right-of-way permit covers "placement of utilities, service lines, private approaches or irrigation facilities" (Appendix B, section 1.09).
- Can the county require boring instead of trenching? Yes — when trenching "may compromise the integrity of the road surface."
- What does the right-of-way permit cost? Not covered on this site; no fee, review time or form number is published in the sources this page is built from. Ask Public Works.
- When is the permit valid for excavation? Only after the 811 notice is given — at least two, at most ten business days before digging starts.
- How long does the locate notice stay fresh? If excavation has not begun within three weeks of the notice, it must be reinitiated.
- Do I have to hand-dig near marked lines? Yes — within twenty-four inches of a marked facility, the precise location must be determined by hand digging.
Where to read next
- Where utilities sit in a county right-of-way — /utilities-in-the-county-right-of-way
- How deep utility trenches go — /how-deep-do-utility-trenches-go
- Call 811 before digging — /call-811-before-digging
- How long locate marks stay valid — /how-long-locate-marks-stay-valid
- The 24-inch hand-dig zone — /the-24-inch-hand-dig-zone-around-marked-utilities
- A crossing on US-20 instead — /getting-a-utility-across-us-20
- Talk to a local operator — (208) 932-1140