How do you get a permit to excavate in a St. Anthony street or right-of-way?
Short answer: You file an application with the St. Anthony City Clerk, pay the $50 fee on the city's form, and wait for the Director of Public Works to approve it — seven steps below. The deadline that bites is the ten-day one: submissions must reach the City Clerk at least ten days before your contemplated construction.
The steps, in filing order
The trigger is any work in the public way: "No person shall engage in any construction, repair, improvement or excavation in any street, alley, easement, or other public right of way within the City without first obtaining a permit …" — a rule "Adopted by Ord. 2024-01 on 1/11/2024" (St. Anthony city code, retrieved 2026-11-23).
| Step | What you do | Who you file with | Cost | Timing | Source |
|---|---|---|---|---|---|
| 1 | Confirm the work is in a street, alley, easement or other public right-of-way | City of St. Anthony — Public Works approves, the Clerk issues | — | — | City code, retrieved 2026-11-23 |
| 2 | Add your insurer's certificate: public liability insurance, single limit, not less than $500,000 | Your insurer | Your policy's cost — not published | — | City code, retrieved 2026-11-23 |
| 3 | File the application | City Clerk — 420 North Bridge Street Suite A, St. Anthony, ID 83445 · Tel 208-624-3494 · Fax 208-624-4003 | "Permit Fee: $50.00" — "To be paid before starting project" | "at least ten (10) days prior to the contemplated construction" | City code; city permit form, retrieved 2026-11-23 |
| 4 | Order the locate before excavating — "PRIOR TO EXCAVATION, CALL DIGLINE (811)" | The city's one-number locator service | Not stated on the pages read | Before excavation | City code; city permit form, retrieved 2026-11-23 |
| 5 | Give notice before work starts | The city | — | 24 to 48 hours before work | City code, retrieved 2026-11-23 |
| 6 | Keep the approved permit at the work site; anything above ground in the right-of-way needs pre-approval and a final inspection before you leave | The city | — | During construction | City permit form, retrieved 2026-11-23 |
| 7 | Backfill, then finish the permanent asphalt repair | Your crew; Public Works or a designee may extend the clock | — | 3 days after backfill; one-year warranty on the patch | City code, retrieved 2026-11-23 |
Where this goes wrong
- You file inside ten days. "All submissions shall be submitted to the City Clerk, at least ten (10) days prior to the contemplated construction within the public rights-of-way."
- You cut a sidewalk, curb or gutter on this permit. It's a separate permit, from the engineer: "It is unlawful for any person to cut, or in any way demolish any sidewalk, curb, gutter and/or curb and parking … without first securing a permit from the engineer so to do."
- You skip the notice window. "Notice shall be given not more than forty-eight hours (48) nor less than twenty-four (24) hours prior to commencing construction, repair, or excavation." Too early fails too.
- The asphalt clock runs out. "Permanent asphalt repairs shall be completed by the permitee not later than three (3) days after the excavation has been back filled, unless otherwise authorized by the Director of Public Works or a designated representative."
What no published source gives you
- A fee newer than the form's $50.00. The code leaves the fee to "a schedule of fees adopted by the City Council by resolution"; no resolution appears on the pages this article uses.
- The sidewalk and curb-cut permit's fee, and any cash deposit for restoration: no amounts are published on the pages read.
- The city's standard drawings and engineering specifications for backfill: adopted by ordinance or resolution, but not among the pages read.
- A traffic control plan, or culvert-specific standards: the first is the Director of Public Works' case-by-case call; the second is all the city publishes on the form's single line about utilities under culverts.
What you file, and what an operator handles
The filings are the owner's: the application to the City Clerk, the insurance certificate, the locate order, and the 24-to-48-hour notice. The excavation, the backfill, the patch inside the three-day clock, and the final inspection are operator work. Describe the job on the homepage form or call/text (208) 932-1140, and we'll introduce you to a local operator.
Questions people ask
- Do I need a permit to excavate in a St. Anthony street or right-of-way? Yes — any construction, repair, improvement or excavation in a city street, alley, easement or other public right-of-way needs one first.
- How much is the permit? The form prints "Permit Fee: $50.00", "To be paid before starting project"; the code leaves the fee to a council resolution, so confirm when you file.
- Do I call 811 before digging in St. Anthony? Yes — the code requires a locate before excavation; the form says "PRIOR TO EXCAVATION, CALL DIGLINE (811)".
- Is a sidewalk or curb cut covered by the same permit? No — cutting or demolishing a sidewalk, curb, gutter or parking strip needs its own permit, secured from the engineer.
- How soon does the street have to be patched? Permanent asphalt repairs are due "not later than three (3) days after the excavation has been back filled", unless the city extends the clock.
Where to read next
- The driveway approach application, walked line by line — Fremont County's process.
- Call 811 before digging — how the locate works.
- Utilities in the county right-of-way — the county-side rules.
- The road you built is warranted for a year — the county's own warranty.