Island Park Excavation
Dirt work in Island Park, Idaho, mapped from the primary sources — the operators, the rules, and the season that governs both
Call or text (208) 932-1140 — local line, free, a person calls back

Published

How much are the state filing fees for a new pond on an Island Park property?

Short answer: The state filing fees for a new Island Park pond run $100.00 to $330.00 for the water-right application, plus $50 to $150 later for the license exam — both priced by storage volume. As of the fee schedules retrieved November 16, 2026, acre-feet stored moves the total most.

What the state charges, item by item

Whether a pond needs storage paper is settled on our pond water-right page; the pond-approvals walkthrough — "What approvals does a new pond in Fremont County need, and in what order?" — orders the rest. This page prices the state's filings only.

The application fee rides with the form: "complete the “Application for Permit” form and submit it to the Department of Water Resources with the required filing fee" — Form I-202 07/24 (retrieved 2026-11-16).

FilingWhen it is paidAmountSource
Water-right applicationWith the application$100.00 at 0.0 – 20.0 AF; $250.00 at 20.1 – 100.0; $290.00 at 100.1 – 200.0; $330.00 at 200.1 – 300.0IDWR filing instructions (Form I-202 07/24), per Idaho Code § 42-221 (retrieved 2026-11-16)
License examinationAt proof of use, when the permit converts to a license$50 at 0.0 – 20.0 AF; $100 at 20.1 – 100.0; $125 at 100.1 – 200.0; $150 at 200.1 – 300.0IDWR license examination fee schedule, per Idaho Code § 42-221 and IDAPA 37.03.02 (retrieved 2026-11-16)
Dam reviewOnly at the regulated-dam size$200 plus $10.00 for each 10 acre-feet or part thereof, at 1,000 acre-feet capacity or lessIdaho Code § 42-1713 (retrieved 2026-11-16)
Stream-channel filingIf the dig touches a live creek$20 statutory filing feeour stream-channel page (published 2026-09-24)

What moves the number

Storage volume. The fee "is based on the proposed storage volume (acre-feet per year or AFY) or on the proposed diversion rate (cubic feet per second or CFS)" — where a proposal carries both, the greater fee governs (retrieved 2026-11-16).

Planned refills. A plan of operation may cover "refills for seepage, evaporation use from storage, and other purposes the applicant intends to replace in the storage facility throughout the year" (same instructions). The tiers key on acre-feet per year, so planned refills can lift the tier.

The dam threshold. Height plus stored water decides whether the dam review fee attaches.

When the dam review fee starts

"Under Idaho Code 42-1711, a regulated dam is an artificial barrier ten feet or more in height from the natural bed to maximum storage elevation that also impounds fifty acre-feet or more." (our pond water-right page, 2026-09-26). Above it, the statute's fee is "two hundred dollars ($200) plus" "ten dollars ($10.00) for each ten (10) acre-feet or part thereof" at 1,000 acre-feet capacity or less — and "Fees submitted shall not be refunded." (Idaho Code § 42-1713, retrieved 2026-11-16)

Below it: "No fee is required for embankments located in low hazard areas if the height is less than 10 feet or reservoir storage is less than 50 acre-feet." That line appears only on IDWR's dam application form, Form 1710/1712 (ver. 2016) — dated; confirm with the Department of Water Resources. The same form notes the dam fee "is additional to other water right application fee(s)."

If the dig touches a live creek

"A $20 statutory filing fee per application. The application is not complete without it, staff review does not begin until it is received, and it is not refunded even if the department determines a permit is not required." (stream-channel-alteration-permit, published 2026-09-24)

What no published source gives you

Where the application goes

Eastern Region, Idaho Dept. of Water Resources, 900 N Skyline Dr, Suite A, Idaho Falls, ID 83402-1718 (retrieved 2026-11-16). The permit later converts to a license at proof of use — the process is on the water-right page. The dig itself is a bid — describe the job on the homepage form, or call or text (208) 932-1140.

Questions people ask

  1. How is the application fee calculated? Storage volume (AFY) or flow rate (CFS), whichever is greater — "determine each fee separately and pay the greater of the two" (retrieved 2026-11-16).
  2. When do I pay the license examination fee? At proof of use, when the permit converts to a license (retrieved 2026-11-16).
  3. Are any of these fees refundable? The dam statute: "Fees submitted shall not be refunded." (Idaho Code § 42-1713); the $20 creek filing says it too.
  4. Under 10 feet and under 50 acre-feet — do I owe the dam fee? No fee, per the 2016 form's low-hazard line; that form is dated, confirm with the Department of Water Resources.
  5. Do these fees pay for the digging? No — they are state filings; the earthwork is a separate bid.

Where to read next