Driveway onto a county road or onto US-20: how do the two approach permits compare in Island Park?
The deciding factor is who owns the road: a county approach is a county form, two signatures and a site visit, while a US-20 approach is an Idaho Transportation Department permit under IDAPA 39.03.42 requiring engineer-stamped plans. State spacing bites hardest: 650 feet between accesses. Figures as published, retrieved August–September 2026.
Two doors, two rulebooks
The site's US-20 page compresses the difference into one sentence: "A county approach on a gravel road is a form and a site visit. A state approach, read straight, brings in a licensed engineer, a traffic control plan for work in the travel lane, and written provision for dust, reclamation and environmental protection." Which door you use is not a choice — it follows the road your lot fronts.
The two approach permits side by side
| Dimension | Onto a Fremont County road | Onto US-20 | Source |
|---|---|---|---|
| Who issues | The county: the application "needs your signature plus two county signatures — Road and Bridge, and Planning and Zoning" | The Idaho Transportation Department, under IDAPA 39.03.42 — "not by the county" | County application; IDAPA 39.03.42 |
| Paperwork | Building Permit number and Parcel ID, plus a sketch of "existing and proposed buildings, retaining walls and other physical features affecting the driveway location" | "construction plans stamped by an engineer licensed in the state of Idaho" | IDAPA 39.03.42.200.11 |
| Fee | The form "prints its fee two ways: $50.00 on the face, $25 per application further down" — which figure is current is not confirmed | An initial fee starts the review; the amount is not in our sources | County form; ITD process |
| Spacing from intersections and neighbors | "a minimum of 125 feet from any intersection" on local roads, 155 feet on collectors, 200 feet on arterials; private approaches "a minimum of 50 feet apart" | "the minimum between unsignalized accesses is 650 feet, and public road spacing is 5,280 feet — a full mile" | County standards; state access rules |
| Width | "20 to 30 feet at the point where the access meets the county road" | "at least 12 feet wide where the posted speed is under 35 mph, at least 20 feet at 35 mph and over, and no more than 40 feet either way" | County code; state standards |
| Geometry | "200 feet of sight distance both ways, meet the road at 80–90 degrees over its last 15 feet, fall away at 2–4 percent, and use a culvert of no less than 18 inches where one is required" | Approaches must comply with "current Department geometric standards and design principles" | County code; IDAPA 39.03.42.400.01 |
| Before any work | "Please call road supervisor before any work is done to be sure the following have been addressed" — Fremont County driveway application, page 3 of 4. Retrieved 11 September 2026 | "No work may start on the right-of-way before the permit issues" | County form; IDAPA |
| Clocks | County review time is not in our sources | Work "must be complete and available for final inspection" within 30 days of starting; "If the permitted work is not complete within a year of issuance, the permit is void" | IDAPA 39.03.42 |
| Built without a permit | "The access is posted with a warning notice and the landowner has ten days to secure an approved application or correct it" | "No activities will be allowed on State highway rights-of-way until an approved permit has been issued by the Department or a delegated local highway agency" | County code; IDAPA |
Choose the county door when
- Your lot fronts a Fremont County road — there is no state permit to file.
- The paperwork you can carry is a form, a sketch, and a site visit rather than engineered plans.
- Your access fits the county spacing table: 125 feet or more from an intersection, 50 feet or more from a neighboring private approach.
Choose the US-20 door when
- Your lot fronts the state highway — the county has no permit to offer.
- An engineer is in the budget from day one, because the review formally begins the day you submit the signed application and pay the initial fee.
- The nearest access point is at least 650 feet away, and any public-road connection a full 5,280 feet — "It is the rule most likely to stop a new approach."
Costs, from published sources only
Neither door has a published total; both are quote items. The county form prints its fee two ways and no page in our sources says which figure is current. On the state side, only the mechanics are published: "The review formally begins the day you submit the signed application and pay the initial fee."
Not covered on this site (named gaps)
- The dollar amount of ITD's initial approach-permit fee, and ITD's review time.
- The county's review time for a driveway application.
- A phone number for the county Road and Bridge office or the ITD district office in Rigby.
- Which of the county form's two printed fee figures is current.
Questions people ask
Does Fremont County issue US-20 approach permits?
No. "US-20 is a state highway, so a new approach onto it is permitted by the Idaho Transportation Department under IDAPA 39.03.42 — not by the county."
Which ITD office handles Island Park?
"Department District offices are located in Coeur d'Alene, Lewiston, Boise, Shoshone, Pocatello and Rigby" — the Rigby office is the near one. — IDAPA 39.03.42.200.04 (retrieved 2026-08-17)
How much are the fees?
The county form prints $50.00 on its face and $25 per application further down; which is current is not confirmed. ITD's initial fee amount is not in our sources — the review begins the day it is paid.
How far apart do driveways have to be?
On county roads, a minimum of 125 feet from any intersection on a local road (155 collector, 200 arterial) and 50 feet between private approaches. On a rural statewide route, 650 feet between unsignalized accesses and 5,280 feet between public roads.
How long is a US-20 approach permit good for?
One year — if the permitted work is not complete within a year of issuance, the permit is void. Once construction starts, the work must be complete and available for final inspection within 30 days.
What happens if I build without the permit?
On a county road, the access is posted with a warning notice and the landowner has ten days to secure an approved application or correct it. On US-20, no activities are allowed on the state right-of-way until an approved permit has been issued.
Related: US-20 approach permits · County road driveway standards · The driveway approach application walkthrough · How far apart driveways can be · How far your driveway sits from an intersection · How wide your approach can be